Leak testing of butt, fillet and lap weld by Vacuum Box Method

Vacuum box testing is a non-destructive examination (NDE/NDT) used for locating welding leaks. A vacuum box and a compressor create a high or low pressure vacuum and a detergent solution is applied to the test area. The detergent bubbles help to identify the leaks within the created pressure envelope. The main objective of this technique is to locate leaks in welds due to through thickness discontinuities. This is accomplished by applying a solution to a weld and creating a differential pressure across the weld causing the formation of bubbles as leakage gas passes through the solution. This testing is to be performed prior to any main vessel or tank testing following the completion of all welding. This article will briefly explain the leak testing procedure that can be used for all metals.

Required Equipment:

  • a compressor: approximate flow 6 m^3 per minute under 7 bar
  • An air pipe between compressor and vacuum box.
  • A vacuum box, which enables to obtain a depression of 500 mbar, which can be controlled by means of a vacuum manometer located on the box. The manometer shall have a range of 0 psi (0 mbar) to 15 psi (1020 mbar).
  • A liquid detergent which mixed with water makes soapy water.
  • Bubble solution which produce a film. That does not break away from the area to be tested and the bubbles formed shall not break rapidly due to air drying or low face tension.
  • Soups or detergents for cleaning shall not be used.
  • If ambient temperature is below freezing, add ethylene glycol to the solution (antifreeze).
  • General lighting or individual lighting if necessary. The minimum light level shall be 100 foot-candles (1000 lux)
  • A brush (diameter not less than 50 mm)
  • A metallic brush and/or a grinding machine.
  • Fig. 1 shows a typical vacuum test box arrangement.
Fig. 1: Typical Vacuum Test Box Arrangement

Test Procedure:

  • Remove weld slag. Mud dirt and other debris from the weld joint, which may prevent bubble formation. This is achieved, if necessary, by strong brushing.
  • If freezing weather conditions exist at the time of the test, heat the weld joint to be vacuum box tested until the metal is slightly warm to the hand in order to avoid any ice, that could possibly be plugging existing leaks. Limit the areas heated to those which can be tested before the metal cools to freezing temperatures. The temperature of the part to be examined shall not be below 40 f (5 ˚c) nor above 125 f (52 ˚c ) during the examination.
  • Provide adequate lighting for this examination.
  • Apply leak detector soap solution to the weld in a continuous film relatively free of bubbles on about 20 inch (500 mm) and on about 4 inch (100 mm) width. This must be achieved at least 1 minute before applying the vacuum box test.
  • Put the vacuum box on the area to be examined:
  • Open the valve of the air ejector.
  • Press on the vacuum box in order to seat it on the plate.
  • Check pressure on the vacuum box manometer: between 204 mbar (3 psi) and 340 mbar (5 psi) Note: the API 620 requirement is a partial vacuum of at least 3 psi.
  • Observe the detector solution for leakage for at least 10 seconds. If there is any leakage, bubbles will appear through the Plexiglas of the vacuum box.
  • Repeat again the operation after having displaced the vacuum box on the welds to be examined. Overlap successive settings of the vacuum box should be at least 50 to 100 mm ( 2 inch to 4 inch), to assure complete coverage of the weld inspected (thickness of the sponge rubber gasket of the vacuum box is about 30 to 35 mm)
  • When testing large areas, such as roof or bottom joints, mark inspected areas to prevent missing an area of weld.

Acceptance Standard: The presence of continuous bubble formation or growth on the surface being examined indicates leakage through an orifice passage(s) in the area under examination. Any indicated leakage shall be considered unacceptable. Some large leaks may not be detected by bubble formation because the strong stream of air may break the bubble film as soon as it forms. To avoid missing this type of leak, the pressure shall be monitored for a variation (decrease).

Repairs: All indicated leaks, regardless of size, shall be marked and repaired by relieving the pressure, removing the defective weld, and re-welding using qualified welding procedures, welders and welding operators, and the repaired area shall be retested by the same steps stated above.

Report:  For all leak testing by means of vacuum box, one report is established by the examiner. This report is reviewed and signed by the constructor quality control supervisor.

Anup Kumar Dey

I am a Mechanical Engineer turned into a Piping Engineer. Currently, I work in a reputed MNC as a Senior Piping Stress Engineer. I am very much passionate about blogging and always tried to do unique things. This website is my first venture into the world of blogging with the aim of connecting with other piping engineers around the world.

Leave a Reply

Your email address will not be published. Required fields are marked *

 

Recent Content

Subscribe For Latest Updates

Signup for our newsletter and get notified when we publish new articles for free!